As of October 2026, a Dubai off-plan handover typically adds, beyond the final instalment, a title-deed fee (AED 580 in several guides), a DEWA deposit (AED 2,000 for an apartment), the first year’s service charge, a snagging inspection and, if still unpaid, the 4% DLD fee. Keys follow only once dues are cleared.

Key figures
- AED 2,000 apartment · AED 4,000 villa
DEWA security deposit (an owner's deposit is refunded only when the premise is sold)
DEWA page, last updated 1 January 2026
DEWA - 10 years
Developer liability for structural defects after handover (one year for installations)
Law No. 6 of 2019, Article 40
Dubai Legislation Portal (Law No. 6 of 2019, Article 40)
- The 4% DLD fee: most sources place it at Oqood registration, but some handover lists carry it “if not already settled”. The sources disagree — Dubai Sotheby’s International Realty, 4 August 2025 against Mortgage Finder, 3 September 2025.
- Title-deed fee: AED 580 at Holo and Mortgage Finder; AED 250 plus AED 20 at Dubizzle.
- DEWA security deposit: AED 2,000 for a flat, AED 4,000 for a villa; an owner’s deposit is refunded only when the property is sold — DEWA, Move-in service fees (last updated 1 January 2026); Engel & Völkers, 9 September 2026 lists the same amounts.
- Snagging inspection, apartment: from AED 800 to AED 3,500 depending on the source — Real Estate Club Dubai, 6 July 2026 and Realty Hunting, 6 October 2026.
- Developer liability after handover: ten years for structural defects from the completion certificate, one year for installations from handover, as one law firm summarises Dubai Law No. 6 of 2019 — Legal 500, 22 October 2024.
Cushman & Wakefield expects about 55,600 homes to be handed over in Dubai in 2026, the highest annual volume since 2008 and around 32,000 of them in the second half (Khaleej Times, 20 August 2026).
What do you pay at handover on a Dubai off-plan unit?
Read this as the usual order of things, not a substitute for your handover notice. Every figure links to its source; where sources disagree, we say so.
- The final instalment: its size and due date sit in the payment plan of your sales and purchase agreement (SPA). Guides commonly quote 5% to 10% of the price; on a 70/30 plan, by its own terms, 30% falls due on completion. If you finance it, the bank releases the payment to the developer, so allow time for the bank’s own process.
- The title deed: when the Oqood converts to a title deed, AED 580 is the commonest figure in the guides; one portal lists AED 250 plus AED 20. The amount on your own receipt is the one that counts.
- Power and water: the DEWA deposit is AED 2,000 for a flat and AED 4,000 for a villa, and for an owner it is refunded only when the property is sold. Activating a small meter is AED 125 on DEWA’s page, and another guide gives AED 130 to AED 155. If your building has district cooling, that is a separate account with its own deposit, and the source gives no amount.
- The developer’s admin fee: paid once to the developer; there is no standard figure, so it should appear on your notice.
- First-year service charge and the snagging inspection: both are covered below.
Do I pay the 4% DLD fee again at handover?
Usually not, but the sources are not unanimous. Dubai Sotheby’s International Realty says the 4% comes with SPA signing and the first payment, and Realty Hunting says it is charged once, at Oqood registration, and not again when the Oqood becomes a title deed. Holo puts “final payment and DLD fees” together at the second step of handover, and Mortgage Finder lists it on the handover checklist “if not already settled”.
Four per cent of a AED 1.5 million unit is AED 60,000 (our arithmetic), so put the registration-stage receipt next to your SPA and see what was actually paid.
When is the final instalment due, and how much notice do I get?
The due date is in your SPA payment plan, and the handover notice triggers it. How long you get is set by the notice itself: Dubizzle and Engel & Völkers both describe a completion notice that gives you about 30 days from its issue date to complete the handover requirements. For you, the text of your own notice and contract is what counts.
The grace period and the penalty for late payment are set in the SPA, not in guides. Read that clause now.
How much does a snagging inspection cost, and what does the developer owe afterwards?
A snagging inspection is a check of the unit’s finish and installations before you sign the handover form. For an apartment the price depends on the source: AED 800 to AED 2,500 in one, AED 1,000 to AED 3,500 in another. Both are published estimates, not a rate card; ask two or three firms to quote your unit.
After handover, the developer’s obligation comes from law. Awatif Mohammad Shoqi Advocates summarise Dubai Law No. 6 of 2019 (Article 40(a)) as making the developer liable for ten years for structural defects, counted from the date it obtains the project’s completion certificate. Mechanical, electrical, plumbing and sewerage installations are covered for one year from handing the unit over to the owner. That is a law firm’s summary, not the text of the law; have your lawyer read the article.
Is the first year’s service charge due at handover?
There is no single answer. Holo says developers charge the annual fee upfront, calculated per square foot. Realty Hunting says it can run from project completion, even before keys.
An adviser in The National’s advice column (28 December 2025) takes the opposite view: the duty to pay begins when you take possession, with the handover notice as the only legal trigger, and an invoice for the period before it is a commercial position, not a legal one. He suggests asking for the billing period and the owners’ association budget approved by RERA.
The amount varies too. Realty Hunting gives a typical AED 10 to AED 35 per square foot per year, while our own service-charge guide quotes AED 3 to AED 30 from the DLD index and explains where to check a building’s approved rate. Ask the developer for yours.
What we would check before the handover notice arrives
This section is the advisory view of Jalili Real Estate. Four things are worth settling before the notice lands.
First, read the sums line by line. For each line on the notice ask what it is for, which SPA clause it comes from, who it is payable to and whether it is refundable. The DEWA deposit and the developer’s admin fee are different things and should not blur into one line.
Second, ask in writing whether you pay before or after you inspect. The guides do not agree on the order: Holo puts the final payment before snagging, while Dubizzle calls the inspection your last chance to spot safety and structural problems. If payment comes first, you have paid before seeing the unit and only the developer’s liability stands behind you. Get the order confirmed in writing, and do not hold back a payment without your lawyer’s advice.
Third, inspect against the contract, not only for flaws. A good inspector compares the unit with the plan and the specification schedule attached to your SPA: materials, dimensions, installations. Give the findings to the developer in writing and ask what signing the handover form means for the defects you have reported.
Fourth, keep a separate budget for the second cheque. This is arithmetic, not a forecast. Take a 1,000 sq ft apartment, a service charge of AED 18 per sq ft (the figure Realty Hunting uses in its own example) and the 4% already paid. The title deed at AED 580, the DEWA deposit at AED 2,000 and activation at AED 125, the first-year charge at AED 18,000 and the inspection at AED 1,000 to AED 3,500 add up to about AED 21,700 to AED 24,200, on top of the final instalment and before any district cooling. If the 4% is still outstanding, that is AED 60,000 more on a AED 1.5 million unit. An owner’s DEWA deposit comes back only when the property is sold (DEWA’s page); most of the rest does not come back at all. Price the registration side with the cost-to-buy calculator (it excludes service charges and utilities) and test what the first year’s charge does to your net yield in the yield calculator.
Related reading: what a Dubai purchase actually costs and buying off-plan, the process end to end; and if you are still choosing a project, five questions that tell you whether an off-plan project is real.
Figures belong to the dates of the sources named, which disagree in places.
Arrange a handover review before the notice arrives — in Farsi or English.
This is general information, not financial or legal advice; check every figure with your adviser before you act.
Do I pay the 4% DLD fee again at handover?
Usually not, but sources disagree. Dubai Sotheby's International Realty (4 August 2025) and Realty Hunting (6 October 2026) place the 4% at SPA or Oqood registration; Mortgage Finder (3 September 2025) lists it at handover "if not already settled". Check your SPA and registration receipt. On a AED 1.5 million unit, 4% is AED 60,000.
How much does a snagging inspection cost in Dubai?
Published estimates for an apartment run from AED 800 to AED 3,500: AED 800 to AED 2,500 at Real Estate Club Dubai (6 July 2026) and AED 1,000 to AED 3,500 at Realty Hunting (6 October 2026). Villas cost more. These are estimates, not a rate card, so ask two or three firms to quote your unit.
Is the first year’s service charge due at handover?
Often it is invoiced then, but sources disagree. Holo says the annual fee is charged upfront; Realty Hunting (6 October 2026) says it can start at project completion. A column in The National (28 December 2025) argues the duty starts at possession. Ask for the billing period.